2012 – Cook Riolo Bridge

Project was to reconstruct the Cook Riolo Road bridge over Dry Creek.

MRPE supported pipeline contractor in maneuvering a constantly changing scope including providing alternate designs for force sewer, potable water and reclaimed water lines thru and around bridge.

This pipeline relocation was supposed to take about 3-months but got extended to about 3-years because of simultaneous instead of subsequent bridge construction. We submitted more than 100 change orders and RFI's, almost all of which were ultimately paid through MRPE supported mediation.